Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
  • More
    • reMIX
    • Company Profiles
    • Events
Latest News

Renewable Podcast Article Example 2

Renewable Podcast Article Example 3

Renewable Podcast Article Example 4

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Daily Email Briefings
  • About Us
  • Advertising with Us
  • Contact Us
reNEWSreNEWS
  • Home
  • Offshore Wind

    Azerbaijan signs offshore wind deal

    December 6, 2025

    LSP Renewables lands Fengmiao contract

    December 2, 2025

    AD Ports and Masdar sign offshore pact

    December 1, 2025

    Ocean Winds hits €2bn BC-Wind financial close

    December 1, 2025

    OWGP awards £2.4m to UK firms

    December 1, 2025
  • Onshore Wind

    McDonald’s UK inks 66MW Scottish wind PPA

    December 2, 2025

    OX2 buys 235MW Romanian wind trio

    December 2, 2025

    Vestas expands Polish blade factory

    December 2, 2025

    Infinity Power starts Ras Ghareb build

    December 1, 2025

    OX2 starts building Ansthall wind farm

    November 28, 2025
  • Solar

    ILOS Energy banks €143m to build Irish solar site

    December 3, 2025

    Zelestra wins 60MW in Italy FER X

    December 2, 2025

    Solar and storage surge in US

    December 1, 2025

    Q ENERGY powers up Cahuzac solar park

    December 1, 2025

    R.Power starts 20MW Klotze solar build

    December 1, 2025
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
  • More
    • reMIX
    • Company Profiles
    • Events
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Energinet drops queue rule for faster connections
Grid

Energinet drops queue rule for faster connections

Stephen DunneBy Stephen DunneNovember 27, 20252 Mins Read
Share Facebook Twitter Bluesky LinkedIn Reddit Copy Link Email
Share
Facebook Bluesky LinkedIn Twitter Reddit Copy Link Email

Energinet will scrap its first-come-first-served principle from 2026 to speed up the connection of the most advanced solar, wind, battery and large electricity-using projects to the transmission grid.
Screening and permitting backlogs have grown as more developers and major consumers seek grid access, and Energinet said it will instead prioritise projects that meet specific maturity requirements and make best use of the existing network.
Kim Willerslev Jakobsen, director for system responsibility at Energinet, said: “The first-come-first-served principle is no longer beneficial, neither for the green transition nor for the plant owners.”
Under the new model, projects will only enter the screening queue if they can document minimum maturity, including the possibility of acquiring required land and providing a timeline covering local planning and environmental permits.
Eligible projects will then be placed in priority groups based on how well they use existing grid capacity and whether a municipal local plan proposal has been adopted.
Projects further along in local authority processes or requiring less grid reinforcement will be prioritised ahead of less advanced schemes, Energinet said.
Stakeholders can submit input on the model until 1 January, with implementation set for 1 February 2026.
Energinet added that the model is a first step and will be followed by further measures to streamline the route to grid connection, while transmission expansion driven by distribution companies will remain unaffected.

Previous ArticleNadara buys out BlueFloat from UK partnership
Next Article Acciona sells South Africa assets to Cennergi

Related News

Zenith signs PPA for major Oz renewables build

December 1, 2025

Nordex opens converter test bench in Rostock

November 26, 2025

ABO Energy cuts earnings outlook for 2025

November 21, 2025
Advertisement

Latest News

Renewable Podcast Article Example 2

February 10, 2026

Renewable Podcast Article Example 3

February 10, 2026

Renewable Podcast Article Example 4

February 10, 2026

Renewable Podcast Article Example

January 21, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}